Upgrading Roads Around Al-Bayt Stadium in Al-Khor

Brief description

The project features the construction of roads leading to the stadium from four directions, as well as providing multiple entrances to the Sports Complex.

Benefits
  • Constructing roads at a total length of 13 km, 5.4 km of which are roads surrounding Al Bayt Stadium from the four sides and consisting of three lanes in each direction.
  • The roads provide direct connection with main roads such as Al-Khor Road and Al Egda Street.
  • Constructing 6 entrances with traffic lights to regulate movement of cars, & 19 designated bus entrances.
  • Constructing 11 km of shared pedestrian and cycle paths.
  • Installing lighting systems using energy saving LED lights and ITS systems, in addition to afforestation and landscaping.
  • Developing Al-Egda Street and constructing a pedestrian path on its sides.
  • Constructing a sewage network, a stormwater drainage network and an irrigation network using TSE.
Project Information
Geographical Location N/A
Area Al Khor
Sector Infrastructure Projects
Total Cost 379,306,184 Q.R.
Status Complete
Type Drainage
Start Date 01 September 2017
Construction company

Bin Omran Trading & Contracting Company

Consulting company

Parsons International Ltd